Aldrich Chemical Co. (Milwaukee Reconstruction)
Chemical plant renovation and new construction in Milwaukee, Wisconsin
Fire Protection Installations:
- Wet systems throughout the lab, liquid storage, and packaging buildings
- Approximately 4,800 sprinkler heads
HVAC Installations:
- Galvanized and stainless steel, and
- FRP (fiberglass reinforced plastic) duct
- Five chillers
- 10 air handlers and rooftop units
- Desiccant unit to reduce humidity
Industrial Process Installations:
- Carbon steel, copper, polypropylene, stainless steel, and CPVCpipe to carry steam, air, water, and a variety of gases
A NOTE ABOUT THIS PROJECT:
“Though bid as a plan and spec job, Ahern has contributed a significant amount of value engineering to keep costs down.”
Heidi Horejs
Senior Project Manager
J. F. Ahern Co.
(click on image for larger photos).
|