Johnson Controls Power SolutionsCorporate headquarters expansion and renovation in Milwaukee, Wisconsin, including three newly constructed buildings and renovation of an existing building. Johnson Controls is seeking LEED (Leadership in Energy and Environmental Design) Platinum certification.
HVAC Installations:
- Central energy plant utilizing a geothermal heating and cooling system
- Solar domestic water heating system
- Three chillers providing 500 tons of cooling
- Three boilers
- 22 base-mounted pumps serving the chillers and boilers
- Six air handling units
- One cooling tower
- Four miles of in-floor radiant tubing
- 32,500 linear feet of PEX, PVC, carbon steel, and copper pipe and tubing
- 230,000 pounds of ductwork
Pipe Fabrication:
- 6,000 linear feet of prefabricated 4” to 12” carbon steel piping