Luther Midelfort Energy PlantHospital energy plant in Eau Claire, Wisconsin
Fire Protection Installations:
- Wet sprinkler system
- Approximately 280 sprinkler heads
- 3,500 linear feet of main and branch pipe
HVAC Installations:
- Central cooling system
- Two 1,000-ton chillers
- Heavy-duty chilled and condenser water pumps
- Two rooftop cooling towers
- Exhaust system and stacks
- Air-handling units and steam-unit heaters
- Radiators for the generators powering the energy plant
- 10,000 linear feet of chilled water, steam, condensate, fuel, and relief piping
- 1,500 linear feet of 10” and 20” diameter underground steam and chilled-water pipe
Plumbing Installations:
- Interior plumbing piping and drains
A Note about this Project:
“Because we had multiple installations on this project, it was vital to maintain open communication…Our ability to effectively manage projects of virtually any size, and exceed customer expectations, reinforces our reputation as one of the finest mechanical contractors in the industry.”
John Haines Project Manager J. F. Ahern Co.
(click on image for larger photos).
|