You are here

Enerpac

Ahern prefabricated and installed over 10,000 feet of air and oil piping to meet the tight deadlines on this manufacturing plant project in Columbus, Wisconsin. Despite a delayed start, prefabricating the pipe reduced the field installation duration by 50% and allowed for the owner’s equipment relocation to start as originally scheduled. Ahern prefabricated the plumbing inwall and industrial piping, including 50 plumbing fixtures, in the 167,100 square-foot building.

Expertise Provided

Values Delivered

Knowledge
  • Ahern’s field team averaged 10 years of experience
Quality
  • No warranty rework
Safety
  • No OSHA recordable events or lost-time injuries