Ahern’s experience with radiography requirements, along with a quick turn delivery schedule, helped land the pipe fabrication work for the Markwest Seneca gas processing facility in Summerfield, OH. Installation of the piping in the compressor building was critical due to the schedule of enclosing the building walls. Ahern’s accurate fabrication of 324 spools, totaling 171,160 pounds, helped the piping fit the first time with minor adjustments and no rework, ultimately avoided installation delays. The project was finished after the estimated completion date due to an engineering redesign. Ahern revised the delivery dates for the piping in that area only, affecting the last of the six total loads.

Expertise Provided

Values Delivered

Knowledge

  • Ahern’s field crew averaged 12 years of industry experience
  • Ahern’s staff held certified welding inspector (CWI) certification which benefitted this specific project

Quality

  •  Ahern’s X-ray pass rate was 96%

Issue Resolution

  •  Ahern was provided the wrong dimensions for the project and communicated the issues right away

Meeting Deadlines

  •  5 of 6 load shipments arrived on-time; the last shipment was delayed due to engineer’s redesign

Budget Certainty

  • 100% on-time completion

Safety

  • No OSHA recordables or lost-time injuries