Monsanto Waco Expansion

Tabs

Overview

Ahern Fire Protection – Omaha served as the prime contractor on this 188,000 square-foot retrofit and 102,000 square-foot expansion project for the Monsanto Waco seed warehouse. Ahern installed nine dry systems – six in the existing warehouse and three in the expansion. Although working around and coordinating with the existing seed storage proved to be a challenge, Ahern was able to build the 250,000 gallon water tank, a pump hose, and install all the underground piping in the expansion without a problem. 

Expertise Provided

Values Delivered

Knowledge

  • Ahern’s office staff averaged 11 years of experience

Quality

  • All designs were approved on the first submission, and required no rework

Safety

  • No OSHA recordables or lost-time injuries