Silver Spur

On-time &within budget

Fire Protection Retrofit Installations for Assisted Living Facilities in the St. Louis Area

With a team that averaged 10 years of experience, Ahern identified and quickly overcame obstacles to retrofitting this St. Louis assisted living facility to include fire sprinkler systems. The largest issue in the turn-of-the-century building was lead contained in the underground domestic water line that would tie to the sprinkler system. Because the lead solder on this pipe was against code, the service line needed replacing. Our team took the initiative to resolve this issue and completed the project on time.

Expertise Provided

Values Delivered

Quality

  • No warranty rework

Schedule Assurance

  • On-time completion

Budget Certainty

  • All work was completed within 1.1% of the original estimate