TVA Lagoon Creek

Tabs

Overview

All prefabricated piping was delivered within the client’s schedule for the TVA Lagoon Creek power plan in Brownsville, Tennessee. This project grew from originally needing 415 pipe spools to fabricating 3,630 spools of carbon steel, chrome, and stainless steel piping for the 550-megawatt combined cycle natural gas power plant. Our team accommodated several schedule priority adjustments, and also spent considerable time mitigating potential on-site issues by rectifying field weld locations on the supplied drawings. Our client was easily able to track the progress of each spool from the daily provided status reports.

Expertise Provided

Value Delivered

Schedule Assurance

  • 100% on-time delivery
  • Shipping notifications were sent prior to all 58 deliveries

Quality

  • 98.1% of our welds passed x-ray testing on the first pass
  • Less than 1% of the piping provided required rework