Fire Protection Installation Services for Power Plants in the Eau Claire Area

In just five weeks, Ahern successfully completed its fire protection design and 560 labor hours to install a deluge fire protection system at Western Wisconsin Energy’s 57 million gallon-per-year ethanol production facility in Boyceville, Wisconsin. This system was required before the plant could transfer ownership. To avoid on-site delays, Ahern held numerous preliminary meetings to better plan its work. It also doubled its installation team.

Expertise Provided

Values Delivered

Knowledge

  • Ahern’s office staff averaged 13 years of experience

Schedule Assurance

  • 100% on-time completion

Quality

  • No warranty rework

Budget Certainty

  • All work was completed within 1.1% of the original estimate