Western Wisconsin Energy (Big River Resources, LLC)
On-timecompletion
Fire Protection Installation Services for Power Plants in the Eau Claire Area
In just five weeks, Ahern successfully completed its fire protection design and 560 labor hours to install a deluge fire protection system at Western Wisconsin Energy’s 57 million gallon-per-year ethanol production facility in Boyceville, Wisconsin. This system was required before the plant could transfer ownership. To avoid on-site delays, Ahern held numerous preliminary meetings to better plan its work. It also doubled its installation team.
Expertise Provided
Values Delivered
Knowledge
- Ahern’s office staff averaged 13 years of experience
Schedule Assurance
- 100% on-time completion
Quality
- No warranty rework
Budget Certainty
- All work was completed within 1.1% of the original estimate