Riverside Energy Center600-megawatt gas-fired power plant in Beloit, Wisconsin
Fire Protection Installations:
- 10 wet pipe sprinkler systems
- Two preaction systems
- Seven deluge systems
- Three foam/water systems
HVAC Installations:
- 16 gas unit heaters
- 31 louvers
- 20 exhaust fans
- Approximately 1,000 linear feet of gas pipe
Industrial/Process Installations:
- Carbon steel, carbon/chrome, stainless steel, and copper pipe
- Pumps, tanks, valves, and process and water treatment equipment
Pipe Fabrication:
Plumbing Installations:
- Cast iron underground pipe
- PVC and copper pipe
A NOTE ABOUT THIS PROJECT:
“We had to put approximately 200,000 man hours in place in 12 months… but we had the resources to get it done.”
David LeMay
Project Manager
J. F. Ahern Co.