Riverside Energy Center

 Riverside Energy Center is a 600 megawatt natural gas fired power plant in Beloit, Wisconsin. Meeting the 12-month construction schedule was critical to begin production of marketable energy. With an average of 86 employees on site during construction, Ahern completed its work on time and within 1.1% of our original estimate. This on-time completion came despite being issued 350 design changes. Our team’s labor coordination, 3D design capabilities, and prefabrication of 2,200 pipe spools came together for a successful execution.

 

Services Provided
- Fire Protection
- Industrial Process
- HVAC
- Plumbing
- Pipe Fabrication

 

Values Delivered
Schedule Assurance
  • On-time completion despite 350 design changes.
  • 86 average crew members, 125 at project’s peak.
Knowledge
  • 10 on-site office personnel, in addition to home office support.
Budget Certainty
  • All work was completed within 1.1% of our original estimate.

 