West Bend WWTPIn 1978, Ahern installed the process piping throughout the West Bend Wastewater Treatment Plant, and it has held up to this day. When the plant’s influent pump header began to fail, Ahern was chosen for the job due to the Company’s outstanding past work performance at this facility.
Pipe Fabrication:
- 12 carbon steel pipe spools
Water/Wastewater Installations:
A NOTE FROM OUR CUSTOMER:
“If Ahern didn’t get the plant back online in time, it would have been disastrous. But there were a lot of ‘thinkers’ on this job, and they made it work.”
Jim Hron
Manager
West Bend Sewer Utility