Cherokee Water Treatment Plant

On timecompletion

Ahern’s pipe fabrication knowledge and ability to meet deadlines were keys to the completion of a fabrication job in Denver, Colorado for the Cherokee Water Treatment Plant. The project consisted of 411 spools of carbon and stainless steel ranging in diameter from 3” to 12”. Being a code shop, Ahern’s welders held the experience and qualifications to fabricate the pipe to the client’s specifications. The project was completed safely with all shipments being delivered on time.

Expertise Provided

Values Delivered

Meeting Deadlines

  • Project was completed on time
  • 3 shipments delivered on time

Quality

  • No warranty rework needed
  • Of the 411 spools, there were no customer-reported problems

Safety

  • No OSHA recordable events or lost-time injuries