Craig Station
On-timecompletion
Pipe Fabrication Services for Power Plants in Colorado
Utilizing their knowledge and experience, Ahern's pipe fabrication team was able to complete this prefabrication job at the Craig Station power plant in Craig, Colorado. Ahern prefabricated 2,495 pounds of stainless steel piping and 79,162 pounds of carbon steel piping equaling 197 total pipe spools (181 carbon and 16 stainless) for this coal power plant. Four different colors of paint were used on this project with all three loads being delivered on-time.
Expertise Provided
Values Delivered
Quality
- No warranty rework needed
Meeting Deadlines
-
All shipments were delivered on-time
Budget Certainty
- Project completed within the original estimate
Safety
- No OSHA recordable events or lost-time injuries