Dominion Brunswick Power Station

On-timecompletion

Pipe Fabrication Services for Power Plants in Virginia

Approximately 1,176 spools, 221,000 lbs., and 13 load shipments later, this pipe fabrication project for a power generation plant in Freeman, VA was completed. Ahern supplied pipe fabrication for 3 identical gas turbine units. Installation of the piping around the turbine was critical due to the limitation of space and confinement. Ahern's bleed air piping fit the first time with minor adjustments and no rework was needed, which helped avoid any installation delays.

Expertise Provided

Values Delivered

Knowledge

  • Pipe fabrication crew averaged 12 years of experience
  • Supplied identical piping on two previous projects for the same customer

Quality

  • No warranty rework needed
  • X-ray testing with 98.3% pass rate

Meeting Deadlines

  • Met the on-site delivery deadline

Safety

  • Zero lost-time injuries
  • No OSHA recordable events