IPL Harding Street

Completed aheadof schedule

Ahern fabricated 505 pipe spools for the IPL Harding Street power plant located in Indianapolis, IN. The successful completion of Units 5 and 6 at the facility earned Ahern the additional work of Unit 7. All units were completed four weeks prior to the final delivery date, keeping the customer’s onsite installation ahead of schedule.

Expertise Provided

Values Delivered

Knowledge

  • Ahern's staff members averaged 10 years of experience
  • ASME Level III certifications

Quality

  • No warranty rework needed

Meeting Deadlines

  • Project completed a month ahead of schedule
  • 6 shipments delivered on time

Safety

  • Zero lost-time injuries
  • No OSHA recordable events