Mid-States Aluminum

Multi-tradeservices

HVAC & Plumbing Services for Manufacturing Plants in the Fond du Lac Area

Ahern finished its work on time and within budget when relocating Mid-States Aluminum’s anodizing line to its 2,500 square-foot addition. Prior to construction, our team generated 3D drawings of the equipment, piping, and ductwork layouts to ensure an efficient layout for the client. Further efficiencies were gained by performing preliminary work prior to finalizing the relocation during a plant shutdown that corresponded with holiday plant closures.

Expertise Provided

Values Delivered

Schedule Assurance

  • All work was completed 3 days ahead of the client’s deadline

Quality 

  • No warranty rework

Budget Certainty

  • Final costs were within the original estimate

Safety 

  • No OSHA recordable events or lost-time injuries