NTE Kings Mountain Energy Center

Qualityassurance

Pipe Fabrication Services for Power Plants in the Carolinas

Ahern fabricated 773 carbon, chrome, and/or stainless steel pipe spools weighing in at 128,337 pounds for the Kings Mountain Energy Center in Cleveland County, North Carolina. Accurate pipe fabrication allowed for the spools to be delivered four weeks early, helping the customer with the installation schedule. To say up-to-date on the project status, Ahern’s pipe fabrication team held daily morning meetings along with weekly shop production meetings.

Expertise Provided

Values Delivered

Quality

  • 98.67% pass rate

Meeting Deadlines

  • Completed project one month ahead of schedule

Safety

  • No OSHA recordable events
  • Zero lost-time injuries